Foundation trenches dug to solid ground which is about 1.1m. Nice hard sandy gravel, but the soil above is soft and crumbly. Had a right job with the sides collapsing in especially where I had to remove the inspection chamber where my foundations would have crossed. It's more of a crater here than a trench!
My idea is to shutter this area off to 600mm then backfill behind the boards. Is this normal practice BC will be ok with?