Hi Im currently doing my bathroom and ensuite so wanting to check the soil stack connections.
the soil pipes are existing and im moving one of the toilets in the bathroom by 90degrees onto another wall.
i plan to install a bend into the vertical stack for toilet number 1 this will be run above the floorboards.
The existing soil stack is running in-between the floor joists and I just want to check that the connections are ok
i have attached a drawing and hope that it explains plus a photo of the existing pipework
Is it ok to have the bath waste bossed into the middle onto a horizontal run of the soil stack. Toilet number 2 is at the end of the branch.
I cannot get to the vertical part of the stack as the bath waste comes through the joist at 90 degrees to the soil pipe. and there is a joist in the way
this is all under the floorboards apart from where im going to install a Tee into the vertical stack. This will be higher than the horizontal run
you can just about see the bath waste appearing through the joist on the other side of the pipe. The tee pokes up through the floor where toilet number 1 use to be I want to remove this and install a plain bit of pipe and use a boss to connect the bath waste to this
does this all seem ok ?
this is how it has been installed when the house was built so i guess it should be ok but looking for re-assurance
cheers
the soil pipes are existing and im moving one of the toilets in the bathroom by 90degrees onto another wall.
i plan to install a bend into the vertical stack for toilet number 1 this will be run above the floorboards.
The existing soil stack is running in-between the floor joists and I just want to check that the connections are ok
i have attached a drawing and hope that it explains plus a photo of the existing pipework
Is it ok to have the bath waste bossed into the middle onto a horizontal run of the soil stack. Toilet number 2 is at the end of the branch.
I cannot get to the vertical part of the stack as the bath waste comes through the joist at 90 degrees to the soil pipe. and there is a joist in the way
this is all under the floorboards apart from where im going to install a Tee into the vertical stack. This will be higher than the horizontal run
you can just about see the bath waste appearing through the joist on the other side of the pipe. The tee pokes up through the floor where toilet number 1 use to be I want to remove this and install a plain bit of pipe and use a boss to connect the bath waste to this
does this all seem ok ?
this is how it has been installed when the house was built so i guess it should be ok but looking for re-assurance
cheers