Hi, I am taking the walls back to brick at the weekend in the living room as they are all blown, I am also removing the door frames as they are totally wrecked and need replacing, my question is what should the order of jobs be, I think I am partially right but unsure, could anyone help? I need to complete this project before XMAS!
- Remove blown plaster from brick (careful around electric cables )
- Give bricks a clean to make sure dot n dab holds
- Plasterboard new ceiling (poking through wires for lights etc)
- Plasterboard the walls (starting from door frame openings, no joints over door frame top)
- Plasterboard the inside of the door frames (is this needed? OR leaving brick?)
- Plaster the room (guy coming to do this)
- Fit new door frame once plaster is all dry (to the new plastered inisdes OR brick?)
- Give new plaster 50/50 coat of emulsion
- Install new skirting boards / architrave etc
- Give walls the final 2 finishes of paint etc
- Have a brew