Hi all,
I am currently in the process of constructing a 15 x 11 concrete slab. Will house a 14 x 10 workshop.
Original plan was to have 3" of sub-base (standard MOT type 1 aggregate) and 3" of concrete in a 5:1 ratio.
I have clay soil that is pretty much dry (mostly).
I have laid all the sub-base today and began compacting it, but it's compacting the clay underneath more than anticipated, so now there's a bigger gap in my concrete shuttering than I had originally planned for.
I am not sure how to proceed.
I have 3" of compacted sub-base. Can I just fill the remaining with concrete or would it be best to fill with more sub-base?
Is this a typical feature of clay soils? Unless I was to lay it in the midst of summer in the baking heat there's always a bit of give in clay soil, so am not sure how this is usually done?
Many thanks in advance,
Daz
I am currently in the process of constructing a 15 x 11 concrete slab. Will house a 14 x 10 workshop.
Original plan was to have 3" of sub-base (standard MOT type 1 aggregate) and 3" of concrete in a 5:1 ratio.
I have clay soil that is pretty much dry (mostly).
I have laid all the sub-base today and began compacting it, but it's compacting the clay underneath more than anticipated, so now there's a bigger gap in my concrete shuttering than I had originally planned for.
I am not sure how to proceed.
I have 3" of compacted sub-base. Can I just fill the remaining with concrete or would it be best to fill with more sub-base?
Is this a typical feature of clay soils? Unless I was to lay it in the midst of summer in the baking heat there's always a bit of give in clay soil, so am not sure how this is usually done?
Many thanks in advance,
Daz