I shall soon be tanking a small shower room: Tilesafe on the floor and Bal WP1 on the walls.
In this instance, should I tank the walls first and then do the floor? I assume that I would get a better seal with the the 75mm wall section of tilesafe on top of the Bal coating, rather than doing job in reverse order.