Good afternoon all.
I was hoping for some advice, we're in the process of getting an extension built (significant build attached to house), and are coming to the final stages.
This work was originally contractually agreed to take around 10 weeks, we are now 6 months in, though the delay is unacceptable and has put massive strains on our lives at home, our biggest concern is the sudden influx in variations that we've neither been quoted for, nor agreed to.
Numerous interim invoices were submitted to us that cover the times that some of this work must have been carried out, however we received no notification, though the original interim costs DID specify variations.
At the beginning of the build we told the builder that our finances were tight, and that we could not afford variations.
Most of the variations carried out, if we'd have been given notice of the extra costs we would have done it our selves without thinking twice, and based on the duration of the build, notice certainly could have been given.
What are our liabilities?
We've shown significant levels of good faith (in my opinion) including paying for an error on his quote where they missed zero resulting in a mid 3 digit sum becoming a mid 4 digit sum, and paying an erroneous invoice allowing him to "amend" the next invoice, which was never done.
I was hoping for some advice, we're in the process of getting an extension built (significant build attached to house), and are coming to the final stages.
This work was originally contractually agreed to take around 10 weeks, we are now 6 months in, though the delay is unacceptable and has put massive strains on our lives at home, our biggest concern is the sudden influx in variations that we've neither been quoted for, nor agreed to.
Numerous interim invoices were submitted to us that cover the times that some of this work must have been carried out, however we received no notification, though the original interim costs DID specify variations.
At the beginning of the build we told the builder that our finances were tight, and that we could not afford variations.
Most of the variations carried out, if we'd have been given notice of the extra costs we would have done it our selves without thinking twice, and based on the duration of the build, notice certainly could have been given.
What are our liabilities?
We've shown significant levels of good faith (in my opinion) including paying for an error on his quote where they missed zero resulting in a mid 3 digit sum becoming a mid 4 digit sum, and paying an erroneous invoice allowing him to "amend" the next invoice, which was never done.