To achieve the necessary depth for underfloor heating & insulation we have to remove a 4 inch concrete slab and replace it.......sounds simple until you discover as we have that all internal walls of this late '60s house are built straight off the slab.
Structural engineer describes this as "outrageous" and i agree...however apart from very slight movement/slope to floor (millimetres) the house remains standing and so do the walls built directly off the slab. One of the (4" thick) walls rises to 1st floor and does not support anything. Two of the (4" thick) walls are load bearing carrying 1st floor joists/floors and then rise to loft level, they are not supporting anything in the loft.
I know from excavations outside that the house foundations are at depth of 1.2M onto sand and gravel, building inspector has been happy with sand and gravel as a base for extensions that I have built.
Regarding underpinning, the two load bearing walls are 2.2M long and run parallel to each other, the non-load bearing wall is approx 2M long and joins each of the load bearers at right angles. (The external cavity wall makes up the box of a room with these three walls..fortunately the cavity wall has a solid foundation.)
I plan to work from one side of the wall, disk cut the existing slab close to the wall and then working a small section (bay) at a time, dig one bay at a time 1.2M deep, shuttering as necessary and concreting up close to the base of the existing slab. Once new foundation has cured we shall dry pack so that the section of wall is completely supported on new concrete foundation. When all bays are complete I shall backfill remaining trench, compact well and then replace the slab.
Does anyone have any advice/experience as to the maximum width of each bay and whether needle or strongboy support is necessary above a certain width of bay? Also any advice as to the width of the new foundation would be helpful, would 300mm be sufficient? (Recognising that i would need to dig at least a 600 wide hole for access & to set up shuttering etc)
Many thanks in anticipation of your replies.
Phil G.
Structural engineer describes this as "outrageous" and i agree...however apart from very slight movement/slope to floor (millimetres) the house remains standing and so do the walls built directly off the slab. One of the (4" thick) walls rises to 1st floor and does not support anything. Two of the (4" thick) walls are load bearing carrying 1st floor joists/floors and then rise to loft level, they are not supporting anything in the loft.
I know from excavations outside that the house foundations are at depth of 1.2M onto sand and gravel, building inspector has been happy with sand and gravel as a base for extensions that I have built.
Regarding underpinning, the two load bearing walls are 2.2M long and run parallel to each other, the non-load bearing wall is approx 2M long and joins each of the load bearers at right angles. (The external cavity wall makes up the box of a room with these three walls..fortunately the cavity wall has a solid foundation.)
I plan to work from one side of the wall, disk cut the existing slab close to the wall and then working a small section (bay) at a time, dig one bay at a time 1.2M deep, shuttering as necessary and concreting up close to the base of the existing slab. Once new foundation has cured we shall dry pack so that the section of wall is completely supported on new concrete foundation. When all bays are complete I shall backfill remaining trench, compact well and then replace the slab.
Does anyone have any advice/experience as to the maximum width of each bay and whether needle or strongboy support is necessary above a certain width of bay? Also any advice as to the width of the new foundation would be helpful, would 300mm be sufficient? (Recognising that i would need to dig at least a 600 wide hole for access & to set up shuttering etc)
Many thanks in anticipation of your replies.
Phil G.