Hi,
I am looking at using Trench/Foundation blocks but I have never used them before and I had a couple of questions:
1. Do you only use them to get up to ground level and then build the cavity wall up to dpc?
2. If I were using standard blocks and had a cavity below ground then you would normally fill with a loose concrete mix and angle the top so any water runs to the external brick leaf. Does a smaller amount of this need doing from the trench blocks near to dpc is it not really required?
Thanks
I am looking at using Trench/Foundation blocks but I have never used them before and I had a couple of questions:
1. Do you only use them to get up to ground level and then build the cavity wall up to dpc?
2. If I were using standard blocks and had a cavity below ground then you would normally fill with a loose concrete mix and angle the top so any water runs to the external brick leaf. Does a smaller amount of this need doing from the trench blocks near to dpc is it not really required?
Thanks