I had building control out today to inspect my foundations which were passed.
Next is the slab, I had intended:
150mm hardcore > sand blinding > membrane > 100mm Kingspan > 100mm concrete slab.
The BCO said vapour barrier between the kingspan and slab.
Is this normal? im guessing it should be the same as the membrane (1000g) and lapping into the DPC with membrane?