Hi All
I want to pour a 6m x 1.2m slab on a sloping driveway. The top edge needs to be flush with the existing level. The slope is 150mm over 1.2m so about 1:8. There is also some cross-slope; about 100mm over the 6m.
I was thinking of excavating to 100mm below the final level. This means part of the base would be flush with ground level, and part would be varying up to 200mm deep as per the attached picture.
How would you shutter this? I was thinking that I might have to use 4x1 for the top and then infill at the bottom by scribing against the top piece and cutting with a jigsaw. To restrain the shuttering I could hammer road pins or rebar pins into the drive every 1m and fix to the shuttering with strapping?
Would you suggest a movement joint half way along the 6m length or would I need more than one?
Would you use mesh? A142?
Thanks