Hi.
At what point do I need to start inserting wall ties. Below DPC or wait until above. I have 2 courses of concrete blocks and 2 courses of engineering bricks below DPC.
Also do I use wall starters below DPC??
Cheers
 
Sponsored Links
Ties every 450 from the bottom of a cavity wall. Whether it's in the ground or above it. But you may want to put ties at the bottom of the insulation to hold it up.

Wall starters above DPC unless you have some sort of whacky design.
 
Sponsored Links
Sorry the second question was referring to the wall starter ties. I have the spacings for the wall ties
 
With wall starters, there will be enough ties for one every block course and one every three brick courses
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top