- Joined
- 28 Feb 2025
- Messages
- 26
- Reaction score
- 4
- Country
Hello again.
My house extension is under way.
The trenches are dug and the concrete is due to be poured tomorrow for the footings. We have got down to a good clay layer that the building inspector is happy with. The only dubious part is at one of the corners. We found a mad, really deep wall, which we think was an old mechanic pit, which people used to have sometimes. The inspector wanted us to dig down to the bottom of the wall (doesn't have a footing) to the clay meaning we've had to step down to it and the ground is aroumd 1.5m deep there. The trouble is, that corner keeps slowly filling up with water, even after we've emptied it, and when we do empty it, the ground is quite soft and sloppy because it is saturated.
If we empty as best we can will it be ok to pour the concrete? I'm wondering if the trickle of water that starts to fill it up by a few inches will screw up the mix? It probably ends up 5" deep in addition to the sloppy clay. The footings will be about 850cm thick in that corner.
Also, as some rain is forecast , will it be sufficient to just put boards over the trenches whilst the concrete sets?
Thanks
My house extension is under way.
The trenches are dug and the concrete is due to be poured tomorrow for the footings. We have got down to a good clay layer that the building inspector is happy with. The only dubious part is at one of the corners. We found a mad, really deep wall, which we think was an old mechanic pit, which people used to have sometimes. The inspector wanted us to dig down to the bottom of the wall (doesn't have a footing) to the clay meaning we've had to step down to it and the ground is aroumd 1.5m deep there. The trouble is, that corner keeps slowly filling up with water, even after we've emptied it, and when we do empty it, the ground is quite soft and sloppy because it is saturated.
If we empty as best we can will it be ok to pour the concrete? I'm wondering if the trickle of water that starts to fill it up by a few inches will screw up the mix? It probably ends up 5" deep in addition to the sloppy clay. The footings will be about 850cm thick in that corner.
Also, as some rain is forecast , will it be sufficient to just put boards over the trenches whilst the concrete sets?
Thanks