Hi
This is probably a little outside the realms of many DIY projects, but here goes. I have a 2200 sq ft, ground floor space (approx 28ft x 78ft). It was, we think, originally built as a dairy or laundry. It has glazed-brick walls, and a roof supported by steel pillars up the centre.
The floor we "inherited" was T+G chipboard over battens. It sloped, badly. We took up that floor, and found what seemed to be a "concrete screed" floor - basically quite a dry mix of concrete, about 4-5 inches thick. . That floor sloped, too.
The sloping was for drainage. The centre of the room (the "long" axis) is a few inches lower than the sides, and one end higher than the other, to allow water to drain.
Anyhow, we dug out the old screed (kango hammers and shovels - about 50 tons in total), and now we have a concrete floor which still slopes, is very uneven (height varies by +/- 4 inches in place), and appears to have been laid in several sections and patched up over many years. That "floor" is also the "slab". Being Victorian, there is no DPM under the slab. There are also various drains (gullies and manholes) in that floor (quite a few of which were simple screeded over before...).
OK, so far, so silly. We can't dig out the slab and start again, for all sorts of reasons, mostly to do with foundations and so on. The finished floor surface we'd like to use is EcoScreed with embedded under-floor heating (pipes).
So the question is how to get from where we are to where we want to be! We've had one "expert" who suggested the following:
- levelling the existing concrete with compacted sand (a lot of it!)
- laying slab insulation (Celotex or similar)
- laying builder's plastic, overlapped and taped
- lay UFH pipes in proprietary plastic "grid" system
- pump EcoScreed over UFH pipes to 50mm or so depth
The net result of this is to create a floating screed, sitting on the insulation.
The main thing I'm concerned about is whether compacted sand at varying thicknesses (0.5 - 5 inches) is a sensible and/or sufficient way to proceed, or whether I'm going to need to put in some concrete first to bring up the levels.
Any thoughts? Thanks!
I also have a problem of having to bring up the manhole / gully levels up, which will mean that they are "rigid" whilst the screed surrounding it will be floating. Any ideas on how best to deal with that for reliability?
Thanks!!
This is probably a little outside the realms of many DIY projects, but here goes. I have a 2200 sq ft, ground floor space (approx 28ft x 78ft). It was, we think, originally built as a dairy or laundry. It has glazed-brick walls, and a roof supported by steel pillars up the centre.
The floor we "inherited" was T+G chipboard over battens. It sloped, badly. We took up that floor, and found what seemed to be a "concrete screed" floor - basically quite a dry mix of concrete, about 4-5 inches thick. . That floor sloped, too.
The sloping was for drainage. The centre of the room (the "long" axis) is a few inches lower than the sides, and one end higher than the other, to allow water to drain.
Anyhow, we dug out the old screed (kango hammers and shovels - about 50 tons in total), and now we have a concrete floor which still slopes, is very uneven (height varies by +/- 4 inches in place), and appears to have been laid in several sections and patched up over many years. That "floor" is also the "slab". Being Victorian, there is no DPM under the slab. There are also various drains (gullies and manholes) in that floor (quite a few of which were simple screeded over before...).
OK, so far, so silly. We can't dig out the slab and start again, for all sorts of reasons, mostly to do with foundations and so on. The finished floor surface we'd like to use is EcoScreed with embedded under-floor heating (pipes).
So the question is how to get from where we are to where we want to be! We've had one "expert" who suggested the following:
- levelling the existing concrete with compacted sand (a lot of it!)
- laying slab insulation (Celotex or similar)
- laying builder's plastic, overlapped and taped
- lay UFH pipes in proprietary plastic "grid" system
- pump EcoScreed over UFH pipes to 50mm or so depth
The net result of this is to create a floating screed, sitting on the insulation.
The main thing I'm concerned about is whether compacted sand at varying thicknesses (0.5 - 5 inches) is a sensible and/or sufficient way to proceed, or whether I'm going to need to put in some concrete first to bring up the levels.
Any thoughts? Thanks!
I also have a problem of having to bring up the manhole / gully levels up, which will mean that they are "rigid" whilst the screed surrounding it will be floating. Any ideas on how best to deal with that for reliability?
Thanks!!