I will need to renovate a property and the big jobs are as follows:
1. New double glazing (including a couple of new external doors)
2. New electrics/lighting throughout (+ alarm, outside lights, A/V and network cabling)
3. New central heating system including rads (convert conventional to combi)
4. Completely decorate three bedrooms, landing and hallway
5. New guttering (not leaking at the moment, just old)
Which order would you do the above in?
What i'm after is advice on when to call in the required builders to do the above and what depends on what.
Also, how long would that little lot take if all the work could be done back-to-back?
1. New double glazing (including a couple of new external doors)
2. New electrics/lighting throughout (+ alarm, outside lights, A/V and network cabling)
3. New central heating system including rads (convert conventional to combi)
4. Completely decorate three bedrooms, landing and hallway
5. New guttering (not leaking at the moment, just old)
Which order would you do the above in?
What i'm after is advice on when to call in the required builders to do the above and what depends on what.
Also, how long would that little lot take if all the work could be done back-to-back?