Not wanting to hijack the other thread but I have a similar question - doing a part integral garage conversion ie insulated stud wall 1.5m behind the garage door to leave a small working area.
For the new habitable room on the inner side of the stud wall we want to use 220mm of PIR insulation to bring the floor level up to match internally - bit chunky I know but it's only a small area so is best way rather than trying to suspend floor.
(Edited to make more sense) Regarding the other existing 2 internal and 1 external walls - from the attached sketch - it's a 70's bungalow and I've had to assume what I can't see going on below - but is there an issue that the internal render / plaster looks to bridge the inner DPC and then if we lay the new DPM how best would we finish it off coming up the wall bearing in mind walls will be reskimmed and the small length of external wall section is having an additional layer of insulated plasterboard, then skimmed and skirting.
Builder from another job and a surveyor have previously checked slab and said in perfect condition, very dry etc so we're assuming there was an initial DPM under the old slab. Walls all clean and dry with no signs of any damp.
On top of flooring PIR will be slip layer, then floor boards, laminate etc.
Thks
For the new habitable room on the inner side of the stud wall we want to use 220mm of PIR insulation to bring the floor level up to match internally - bit chunky I know but it's only a small area so is best way rather than trying to suspend floor.
(Edited to make more sense) Regarding the other existing 2 internal and 1 external walls - from the attached sketch - it's a 70's bungalow and I've had to assume what I can't see going on below - but is there an issue that the internal render / plaster looks to bridge the inner DPC and then if we lay the new DPM how best would we finish it off coming up the wall bearing in mind walls will be reskimmed and the small length of external wall section is having an additional layer of insulated plasterboard, then skimmed and skirting.
Builder from another job and a surveyor have previously checked slab and said in perfect condition, very dry etc so we're assuming there was an initial DPM under the old slab. Walls all clean and dry with no signs of any damp.
On top of flooring PIR will be slip layer, then floor boards, laminate etc.
Thks
Attachments
Last edited: