When changing consumer unit to new split load type
noted during installation and testing that there is no supplementary bonding in bathroom, shower has no pull cord isolating switch , no sleeving on cpc's
would these all be noted on eic or would the work have to be carried out to bring up to standard before finalising certificate
thank you
noted during installation and testing that there is no supplementary bonding in bathroom, shower has no pull cord isolating switch , no sleeving on cpc's
would these all be noted on eic or would the work have to be carried out to bring up to standard before finalising certificate
thank you