Hi
I'm putting together a contract for a side extension which is part single storey and part double storey. The builder is fitting/tiling the bathrooms but is not responsible for the heating or windows.
I've put together a payment schedule which I hope is fair to him and allows him adequate cash flow. However I also need to make sure that I'm never in a position where I've paid a lot more in excess of the work I've had done. (Just in case he goes bust or somebody else has to be paid to rectify something)
This is what I've come up with.
1) Day of arrival on site = 5%
2) Completion of footings =10%
3) Completion of brickwork to ground floor. =15%
4) Completion of brickwork to roof plate of first floor =20%
5) Completion of roof structure =10%
6) Completion of first fix electrical installation = 10%
7) Completion of plastering = 5%
Second fix inc bathrooms, tiling = 5%
9) Completion inc site clearance, external painting =15%
10) Snagging deposit of 5% to be retained for three months, or until building regs sign off/electrical certificate supplied (whichever is later)
Also, there will be significant knock throughs into the existing house needing lots of steel. Where should I position this in the schedule?
Many thanks for your help
I'm putting together a contract for a side extension which is part single storey and part double storey. The builder is fitting/tiling the bathrooms but is not responsible for the heating or windows.
I've put together a payment schedule which I hope is fair to him and allows him adequate cash flow. However I also need to make sure that I'm never in a position where I've paid a lot more in excess of the work I've had done. (Just in case he goes bust or somebody else has to be paid to rectify something)
This is what I've come up with.
1) Day of arrival on site = 5%
2) Completion of footings =10%
3) Completion of brickwork to ground floor. =15%
4) Completion of brickwork to roof plate of first floor =20%
5) Completion of roof structure =10%
6) Completion of first fix electrical installation = 10%
7) Completion of plastering = 5%
Second fix inc bathrooms, tiling = 5%
9) Completion inc site clearance, external painting =15%
10) Snagging deposit of 5% to be retained for three months, or until building regs sign off/electrical certificate supplied (whichever is later)
Also, there will be significant knock throughs into the existing house needing lots of steel. Where should I position this in the schedule?
Many thanks for your help