Morning all
I have had velux windows installed in my loft. The plans advised that the rafters needed to be doubled up to the ridge
The builder has unfortunately not gone all the way to the ridge, therefore the SE is not happy and won't sign off.
The builder came back to extend the rafters, as shown in the below photos. Sadly, the SE still won't accept the remedial work and he wants full length rafters put in.
Builder is advising this would require windows to be taken out and roof peeled back and a full lid for scaffolding.
I want to avoid that as I just want it done.
Builder is having a new SE look at the remedial work and hope we can find a solution.
Our SE won't budge BTW.
It is a nightmare scenario. I struggle to understand why plans are never followed.
Any ideas on the following:
1. What do you think of the remedial work carried out by the builder?
2. is there anything we can do to further add to the structure to get it passed BC?
3. If I have a new structure engineer provides a resolution do I need new drawings for the whole house or can I just add drawings for the roof?
I have had velux windows installed in my loft. The plans advised that the rafters needed to be doubled up to the ridge
The builder has unfortunately not gone all the way to the ridge, therefore the SE is not happy and won't sign off.
The builder came back to extend the rafters, as shown in the below photos. Sadly, the SE still won't accept the remedial work and he wants full length rafters put in.
Builder is advising this would require windows to be taken out and roof peeled back and a full lid for scaffolding.
I want to avoid that as I just want it done.
Builder is having a new SE look at the remedial work and hope we can find a solution.
Our SE won't budge BTW.
It is a nightmare scenario. I struggle to understand why plans are never followed.
Any ideas on the following:
1. What do you think of the remedial work carried out by the builder?
2. is there anything we can do to further add to the structure to get it passed BC?
3. If I have a new structure engineer provides a resolution do I need new drawings for the whole house or can I just add drawings for the roof?