We are about to put in the 1st floor joists on a 2 story extension.
On the plans it shows an area (where new stairs will pass thru) that requires double and treble joists.
Question 1; do we use 2 joist hangers side by side for each joist or do we use 1 joist hanger and bolt the second joist to the supported joist.
Also we need to place a small piece of joist (trimmer) between main joists, do we hang this using joist hangers that hang off the joist sideways (90 degree)
Thanks