After a bit of advice. We've had 4 builders round to quote on the following work and only one has got back to us with a price of 3k. I was expecting 1.5 to 2k based on my estimates of materials and time:
- use electrician to move internal double socket 400mm to side (£150?)
- divert single storey soil stack 1m to side (materials £100 at most, no ground works needed, all builders have said it's a "quick easy job") = £100 materials plus half day labour.
- cut opening and install lintel for new window in solid brick wall (single storey, easy access, nothing in the way on either side once soil stack is diverted, concrete lintel sufficient as walls are rendered) = £100 materials(?) plus 2 man days labour.
- supply and fit new window in opening, and replace adjacent window with same type (estimate of £200 per window max for supply) = £500 materials plus half man day labour
- make good render on outside, plaster on inside (no window board as it'll be tiled) = £100 materials plus half man day labour.
At £250/day labour rate (bit of a guess but sounds generous), that would come to £875 (3.5 days), and materials would come to approx. £800. Including electrician for the socket at the start, the total I estimated was £1725.
Is there something I'm missing? I've told builders I'll sort a skip and building control.
- use electrician to move internal double socket 400mm to side (£150?)
- divert single storey soil stack 1m to side (materials £100 at most, no ground works needed, all builders have said it's a "quick easy job") = £100 materials plus half day labour.
- cut opening and install lintel for new window in solid brick wall (single storey, easy access, nothing in the way on either side once soil stack is diverted, concrete lintel sufficient as walls are rendered) = £100 materials(?) plus 2 man days labour.
- supply and fit new window in opening, and replace adjacent window with same type (estimate of £200 per window max for supply) = £500 materials plus half man day labour
- make good render on outside, plaster on inside (no window board as it'll be tiled) = £100 materials plus half man day labour.
At £250/day labour rate (bit of a guess but sounds generous), that would come to £875 (3.5 days), and materials would come to approx. £800. Including electrician for the socket at the start, the total I estimated was £1725.
Is there something I'm missing? I've told builders I'll sort a skip and building control.