Hi there
In the early stages of planning my extension and am hoping to do the groundwork, footings,drains and up to dpc myself. May also do the cavity brickwork but will see at the time. The job can be split into sections which although not ideal will give me more chance of being able to break it into manageable chunks, obviously was planning on pouring the foundations in one go but would it be OK to say build up one section and add the garage on the side at a later stage building off it using wall starters?
In the early stages of planning my extension and am hoping to do the groundwork, footings,drains and up to dpc myself. May also do the cavity brickwork but will see at the time. The job can be split into sections which although not ideal will give me more chance of being able to break it into manageable chunks, obviously was planning on pouring the foundations in one go but would it be OK to say build up one section and add the garage on the side at a later stage building off it using wall starters?