Hello,
Had the idea of adding an extension onto the side of the house for a while and have only just decided to put some serious thought into it.
We bought the house in 2014 and have got the plans for the garage (joined to house) which was built circa 1994. The plans show that the foundations were done via trench fill and are 600mm wide x 1000m deep. The garage is built single skin but has supporting brick columns every 2.2m along the length of the wall. So in essence two brick with no cavity at those points.
We had building control out six months ago just to ask some questions and they advised that provided the columns are built off the footings, we would be able to use steels on top of these to build the inner skin off providing that structural calcs are provided. This would then mean insulating the internal walls to get the right U values.
I've been out and dug a test pit this morning and have found that we have two bricks below ground level and then the concrete depth is 650mm beneath this onto solid red clay, 850 ish all in. Width was 700mm
Where do I stand with this? Could it be that they are just shallower at the end of the trench? If building control verified that they were 1m deep in 1994 doesn't this decision still stand?
Going to give them a call and see what they say but wanted to ask the real experts on here before I progress any further. I don't fancy underpinning as it wouldn't be worth it, we're talking 14m worth and cutting the garage floor up if so.
Thanks, Matt
Had the idea of adding an extension onto the side of the house for a while and have only just decided to put some serious thought into it.
We bought the house in 2014 and have got the plans for the garage (joined to house) which was built circa 1994. The plans show that the foundations were done via trench fill and are 600mm wide x 1000m deep. The garage is built single skin but has supporting brick columns every 2.2m along the length of the wall. So in essence two brick with no cavity at those points.
We had building control out six months ago just to ask some questions and they advised that provided the columns are built off the footings, we would be able to use steels on top of these to build the inner skin off providing that structural calcs are provided. This would then mean insulating the internal walls to get the right U values.
I've been out and dug a test pit this morning and have found that we have two bricks below ground level and then the concrete depth is 650mm beneath this onto solid red clay, 850 ish all in. Width was 700mm
Where do I stand with this? Could it be that they are just shallower at the end of the trench? If building control verified that they were 1m deep in 1994 doesn't this decision still stand?
Going to give them a call and see what they say but wanted to ask the real experts on here before I progress any further. I don't fancy underpinning as it wouldn't be worth it, we're talking 14m worth and cutting the garage floor up if so.
Thanks, Matt
Attachments
Last edited: