Filling UK Networks application for relocating meter

Joined
18 Jan 2013
Messages
6
Reaction score
0
Location
London
Country
United Kingdom
I am making an application to have a single supply divided into two and relocate the meters in the entrance hall. I need help with filling section E as shown below.

Section E - Upgrade
Existing Power: KVA Single Phase
Required Power: KVA Single Phase (up to 23kva)

I took the following information from an electrician and may have noted it incorrectly:
Eiisting Power: 100 KVA Single Phase
Required Power: 60 Amp KVA Single Phase (up to 23kva)

Thank you in advance for your help
 
Sponsored Links
I think you've got your units a bit mixed up...

V = Volts
A = Amps
VA = Volts x Amps
kVA = Volts x Amps /1000

In a normal domestic installation you will likely have 230 Volts x 100 Amps = 23000 VA or 23 kVA

or 230 Volts x 60 Amps = 13800 VA or 13.8 kVA

Not sure why you'd want to downgrade from 100A to 60A though?
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Sponsored Links
Back
Top