So my building controller says Lath and plaster ceilings do not meet the 30 min fire protection, so as part of our loft conversion we are required to insert rockwool Flexi within a galvanised steel mesh between the joists in the floor above.
My LBC says since grenfell they no longer accept intumescent paints on the L & P. I retouched this topic with him recently and he seemed to get a bit angry and suggests we've covered this and they're no longer accepted. I'm just not quite sure why?
The intumescent paint is costly but I suspect still cheaper than the labour cost of pulling up all the skirting boards and original floorboards.
Is this something others have encountered in different regions? I'm in east Devon.
I'm reluctant to pull the lot down and replace with gypsum. seems so wasteful.
My LBC says since grenfell they no longer accept intumescent paints on the L & P. I retouched this topic with him recently and he seemed to get a bit angry and suggests we've covered this and they're no longer accepted. I'm just not quite sure why?
The intumescent paint is costly but I suspect still cheaper than the labour cost of pulling up all the skirting boards and original floorboards.
Is this something others have encountered in different regions? I'm in east Devon.
I'm reluctant to pull the lot down and replace with gypsum. seems so wasteful.