just register, hello everyone:
I am Converting my loft into living space.
My rafters are 4x2. hold up by single purlin from wall to waal is about 7m.
The space is very tight so i am dlowering dowm ceiling below to achieve more headroom into loft.
To do this new floor joist will run from wall to wall not at eaves level (just below) so the new joists will not tie togeter the roof structure.
The arquitect seems reluctant to give a solution to this, but this will be the cheapest option for me as I dont want to take the whole roof up as he is suggested.
Is anyboby come across this problem before ??
How to we hold the roof together ??
Hope I make sense.
thanks.
I am Converting my loft into living space.
My rafters are 4x2. hold up by single purlin from wall to waal is about 7m.
The space is very tight so i am dlowering dowm ceiling below to achieve more headroom into loft.
To do this new floor joist will run from wall to wall not at eaves level (just below) so the new joists will not tie togeter the roof structure.
The arquitect seems reluctant to give a solution to this, but this will be the cheapest option for me as I dont want to take the whole roof up as he is suggested.
Is anyboby come across this problem before ??
How to we hold the roof together ??