After reading a number of shed threads it got me thinking of how I might tackle such a project, (assuming I had a shed worth electrifying), and I came up with the following 'Method Statement'.
Please feel free to constructively criticise or advise.
To Install Electric Supply to a Shed.
(All work to comply to BS7671: 17th Edition)
1/ To use 3 core, 6mm^2 SWA as the supply cable, buried in trench at a minimum depth of 460mm, encased in underground ducting and marked with a 'Warning' tape directly above.
2/ Mount an IP65 rated 'Garage CU' externally directly behind a 13A socket which is mounted inside the lounge and which has been confirmed as being part of the 32A ring main and not a spur.
3/ Cable to be run from internal socket box through 20mm conduit into external CU, (this cable is NOT to be connected to socket until all other connections have been made and tested accordingly). On exiting CU cable is to be correctly glanded using 20mm cw gland before entering trench.
4/ Cable to be routed to shed as per item 1 and terminated at a 30A double pole isolating switch inside the shed.
5/ From the double pole switch a 20A Radial circuit to be run to 2 double gang sockets using 2.5mm T&E and a single, switched, lighting circuit using 1.5mm T&E to be installed.
6/ All work to be carried out in a professional manner and tested to current IEE regulations and all relevant certificates completed.
7/ Trench to be back-filled with gravel to discourage any future planting taking place in area of cables.
Please feel free to constructively criticise or advise.
To Install Electric Supply to a Shed.
(All work to comply to BS7671: 17th Edition)
1/ To use 3 core, 6mm^2 SWA as the supply cable, buried in trench at a minimum depth of 460mm, encased in underground ducting and marked with a 'Warning' tape directly above.
2/ Mount an IP65 rated 'Garage CU' externally directly behind a 13A socket which is mounted inside the lounge and which has been confirmed as being part of the 32A ring main and not a spur.
3/ Cable to be run from internal socket box through 20mm conduit into external CU, (this cable is NOT to be connected to socket until all other connections have been made and tested accordingly). On exiting CU cable is to be correctly glanded using 20mm cw gland before entering trench.
4/ Cable to be routed to shed as per item 1 and terminated at a 30A double pole isolating switch inside the shed.
5/ From the double pole switch a 20A Radial circuit to be run to 2 double gang sockets using 2.5mm T&E and a single, switched, lighting circuit using 1.5mm T&E to be installed.
6/ All work to be carried out in a professional manner and tested to current IEE regulations and all relevant certificates completed.
7/ Trench to be back-filled with gravel to discourage any future planting taking place in area of cables.