Hi guys,
I'm not sure if this topic has already been discussed but could really do with some advice.
I bought my property last year and it has some plans which were passed in 1980. Part of the work was started and completed within a short time of the planning permission being granted. I now want to carry on with that scheme and complete the work as per the passed plans.
My question is, is there a time limit as to when the planning permission would expire in this case as building work had commenced within 3 years of permission being granted?
I have spoken to my local planning office and not been given a clear answer based on anything firm or following any rules or guidelines.
I was initially told that if the building work did commence within 5 years as that was the set limit at the time for starting the work then there is no limit on how long you have to complete the work. The same person then went away and came back on the phone and backtracked by saying it would be safer to submit new plans in case they ask me to remove the new part.
I have submitted plans to my local council to build a 2 story side extension which has been rejected twice and also been through appeals and had it rejected. So I am very frustrated and have spent a lot of time and money and not even started to build yet.
I would really appreciate some advice on this.
Many thanks.
I'm not sure if this topic has already been discussed but could really do with some advice.
I bought my property last year and it has some plans which were passed in 1980. Part of the work was started and completed within a short time of the planning permission being granted. I now want to carry on with that scheme and complete the work as per the passed plans.
My question is, is there a time limit as to when the planning permission would expire in this case as building work had commenced within 3 years of permission being granted?
I have spoken to my local planning office and not been given a clear answer based on anything firm or following any rules or guidelines.
I was initially told that if the building work did commence within 5 years as that was the set limit at the time for starting the work then there is no limit on how long you have to complete the work. The same person then went away and came back on the phone and backtracked by saying it would be safer to submit new plans in case they ask me to remove the new part.
I have submitted plans to my local council to build a 2 story side extension which has been rejected twice and also been through appeals and had it rejected. So I am very frustrated and have spent a lot of time and money and not even started to build yet.
I would really appreciate some advice on this.
Many thanks.