Hi there
I have a wall remove and building control want a footing to be installed. The floor inside and outside are two different levels.
How can I prop up the RSJ so I can dig under a spreader beam, can I use two acro's and a beam between them?
The RSJ is supported by two steal posts bolted to the wall but the spreader beam needs a footing installed and I cannot think how to prop up the sway frame
I have a wall remove and building control want a footing to be installed. The floor inside and outside are two different levels.
How can I prop up the RSJ so I can dig under a spreader beam, can I use two acro's and a beam between them?
The RSJ is supported by two steal posts bolted to the wall but the spreader beam needs a footing installed and I cannot think how to prop up the sway frame