UFH difference in insulation height between kitchen and hall

Joined
13 Dec 2022
Messages
59
Reaction score
1
Country
United Kingdom
So the finished insulation floor height in my kitchen is about 12mm lower than the hallway due to an issue with the concrete depth being off to what was specified. The wet ufh loops are going to all rooms downstairs and for the kitchen loop it will need to cross this 12mm height difference, the kitchen will end up with a slightly deeper flow screed level as a result, but I just want to check that this will still work ok? i.e. the pipes will end up with flow screed supporting under the transition point to the room. I'm hoping it's going to be ok, best laid plans and all that
 
Sponsored Links
If the flow screed is being poured for ground floor completely, or at least the kitchen and hall together I can't see any issues.

For me I'd say a join at the kitchen/hall meeting point may possibly cause an issue with any settlement but a smarter guy than I should answer that!
 
It will be fine

What depth of insulation have you put down, btw? Have you made sure there is a border of insulation all the way round the edge of where the screed will be poured? Have you made sure to leave ducts for services for things like kitchen islands and the manifold supply?
 
Last edited:
It will be fine

What depth of insulation have you put down, btw? Have you made sure there is a border of insulation all the way round the edge of where the screed will be poured? Have you made sure to leave ducts for services for things like kitchen islands and the manifold supply?
150mm pir in the kitchen, complete dig out. and 225mm in the other rooms which used existing concrete slab below suspended floor. We've got eps70 25mm upstands all around walls internal and external.
 
Sponsored Links
eps70 25mm upstands
Oof, all that really good thickness of PIR and then such a skinny bead of poorer performing insulation on the colder parts of the structure.. If you've got time, I'd consider changing it out for 50mm PIR
 
Oof, all that really good thickness of PIR and then such a skinny bead of poorer performing insulation on the colder parts of the structure.. If you've got time, I'd consider changing it out for 50mm PIR
Building Inspector suggested not to use pir for the upstand. I had originally planned to use it
 
"Because density"

What does that even mean? What's the logic behind isolating the slab from the ground using a good amount of insulation, and then using insulation that's 15 times worse to isolate the same slab from a part of the structure that is directly connected to the ground you spent a huge amount of money and effort isolating the slab from?
 
Last edited:
I have both on my UFH, insulated upstand and foam compression layer.
 
"Because density"

What does that even mean? What's the logic behind isolating the slab from the ground using a good amount of insulation, and then using insulation that's 15 times worse to isolate the same slab from a part of the structure that is directly connected to the ground you spent a huge amount of money and effort isolating the slab from?
PIR isn't recommended due to it been so dense as it doesn't have sufficient flexibility for slab expansion (apparently). The upstand I thought was only to prevent cold bridging with the walls, there isn't the same contact surface to be a major issue, or perhaps I'm missing something? I've not seen anyone use or recommend 50mm pir before when scouring forums on upstands. I'm a novice though so happy to be enlightened on the subject.
 
I used 50mm PIR for cold bridging, then a foam compression roll for expansion, think its around 12-15mm thick.
The floor won't move that much.
 
Use polystyrene for your upstand if you are worried about it, as this compresses more than PIR
 
it doesn't have sufficient flexibility for slab expansion
anhydrite screeds expand at a rate of 0.012mm per meter, per degree. In essence this means if your house is 10 metres wide, and your screed is laid and dries at 15 degrees C, when you run it at 27 degrees C, the floor will expand by 0.7mm on each side of the room.

One of three possible things could happen when the floor expands

* The walls and PIR are so strong, the screed will bow up in the middle by 73.5mm
* The screed and the PIR are so strong, the walls will be shoved outwards along the foundations by 0.7mm
* The PIR, which won't be hard up against the wall or the screed, will compress by 0.7mm

If you're in any doubt as to which of these will occur, just press on the surface of a PIR board with your fingers next time you have one to hand
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Sponsored Links
Back
Top