I am at the info gathering stage at the moment (intend to do the work approx 2 mnths time) and have read quite a lot of the threads so far for the background info.
Background, I am refurbishing an old water mill which was renovated approx 1975. Although the wiring is in very good condition its a bit untidy and doesn't seem particularly well planned out. It is run off 3 old wylex boards, situated next to each other. I am pretty sure I know what I want to do, but I would like a bit of advice. The building is currently split into two, the other side requires complete refurbishment including wiring.
My background is electrical engineering (however I haven't been a practising engineer for about 8years) - and this was industrial electrics not domestic.
The overall aim is to:
- install a 16a welding socket into the garage, this is also to double up as a generator infeed for the house electrics in the event of power failure
- remove the 3 wylex boards and replace with one CU
- rewire the other side of the building with its own CU,
The house is, as far as I can tell, a TT system, but there isn't an RCD - yet.
Work intended (probably in order, this is the easiest/ safest way it would be for me), and council permission that I think I need:
1. Install a isolator between the meter and wylex boards, including henleys. The old boards will then be reconnected to the henleys with 25mm tails (they are currently a lot thinner). I don't believe that this is part P covered
2. Install a 4mm SWA cable through a fuseable isolator to the garage, feeding from the henleys. This will then act as a welding socket, and (if I isolate the henleys from the grid) I can connect a generator up to the house boards (if this makes sense). I don't believe that this is part P covered.
3. Change the old wilex boards to a new CU. crimping the cables to extend where necessary. I don't believe that this is part P covered
The next bit I think is part P covered, as it will involve wiring a kitchen up, (or what will be a kitchen when it is finished). I intend to notify the council and then do the work ready for their inspection before it is powered up.
4. run 2 single 25mm tails from the henleys to the location of the CU approx 15m away. Install CU and run necessary lighting and ring mains ect.
Questions:
- is the above realistic
- the new CU will have RCD's in then, will I still require an RCD on the incomer - ie between the meter and the henleys (I don't really want to put one there)..
- what size earth will I require for the new CU, I was planning on using a 16mm. Not sure what size the earth cable is to the earth spike
- I need an isolator for any tails over 3m, will the isolator between the meter and the henleys be acceptable, or does the new CU need its own isolator.
- given the untidiness of the 3 wylex boards i am expecting to find some unusual rings in place, can I
- if I find a two socket rings that cover the same area (assuming they are both 2.5mm, can I connect 2 rings to the same fuse. I would like to put all the downstairs sockets on the same fuse, downstair lights on a single different fuse ect.
- if I find several spurs off the wilex boards, using the same size cable, is it acceptable to connect more than one spur to a single fuse
I have some other digging about to do with regards to info about the current system, I want to know exactly what I have before I start to pull it apart.
Thanks for any advice, I know once I plan it out better I will probably have some more questions
Steve
Background, I am refurbishing an old water mill which was renovated approx 1975. Although the wiring is in very good condition its a bit untidy and doesn't seem particularly well planned out. It is run off 3 old wylex boards, situated next to each other. I am pretty sure I know what I want to do, but I would like a bit of advice. The building is currently split into two, the other side requires complete refurbishment including wiring.
My background is electrical engineering (however I haven't been a practising engineer for about 8years) - and this was industrial electrics not domestic.
The overall aim is to:
- install a 16a welding socket into the garage, this is also to double up as a generator infeed for the house electrics in the event of power failure
- remove the 3 wylex boards and replace with one CU
- rewire the other side of the building with its own CU,
The house is, as far as I can tell, a TT system, but there isn't an RCD - yet.
Work intended (probably in order, this is the easiest/ safest way it would be for me), and council permission that I think I need:
1. Install a isolator between the meter and wylex boards, including henleys. The old boards will then be reconnected to the henleys with 25mm tails (they are currently a lot thinner). I don't believe that this is part P covered
2. Install a 4mm SWA cable through a fuseable isolator to the garage, feeding from the henleys. This will then act as a welding socket, and (if I isolate the henleys from the grid) I can connect a generator up to the house boards (if this makes sense). I don't believe that this is part P covered.
3. Change the old wilex boards to a new CU. crimping the cables to extend where necessary. I don't believe that this is part P covered
The next bit I think is part P covered, as it will involve wiring a kitchen up, (or what will be a kitchen when it is finished). I intend to notify the council and then do the work ready for their inspection before it is powered up.
4. run 2 single 25mm tails from the henleys to the location of the CU approx 15m away. Install CU and run necessary lighting and ring mains ect.
Questions:
- is the above realistic
- the new CU will have RCD's in then, will I still require an RCD on the incomer - ie between the meter and the henleys (I don't really want to put one there)..
- what size earth will I require for the new CU, I was planning on using a 16mm. Not sure what size the earth cable is to the earth spike
- I need an isolator for any tails over 3m, will the isolator between the meter and the henleys be acceptable, or does the new CU need its own isolator.
- given the untidiness of the 3 wylex boards i am expecting to find some unusual rings in place, can I
- if I find a two socket rings that cover the same area (assuming they are both 2.5mm, can I connect 2 rings to the same fuse. I would like to put all the downstairs sockets on the same fuse, downstair lights on a single different fuse ect.
- if I find several spurs off the wilex boards, using the same size cable, is it acceptable to connect more than one spur to a single fuse
I have some other digging about to do with regards to info about the current system, I want to know exactly what I have before I start to pull it apart.
Thanks for any advice, I know once I plan it out better I will probably have some more questions
Steve