Is there a kind person out there who can help me understand if these 2 quotes are comparable? One seems much longer than the other but with my practically non-existent technical knowledge, they both seem to be saying more or less the same thing. In a nutshell, is one offering more than the other or are they pretty much like-for-like? Many thanks!
Quote 1 - Vaillant ecoTec Plus 30 System boiler
Isolate supplies and drain down water.
Disconnect and remove the existing radiators, boiler and flue.
Supply and install a new Vaillant system boiler and flue to the Cupboard.
Supply and install a system filter.
Supply and install a new 250L unvented hot water cylinder to the Airing Cupboard.
Supply and install new radiators with thermostatic valves to 12 rooms.
Fill the system and flush out, refill with added corrosion inhibitor.
Carry out system water test and report back if there are any issues.
Removal of all waste from the site for recycling/disposal.
Set up and test of the whole system, including a full handover and explanation of the system and controls.
Commission and issue manufacturer's warranty*
Quote 2 - Worcester Greenstar 4000 System boiler 24kW
SUPPLY & FIT:
BOILER
A Worcester Bosch Greenstar 4000 24kw, wall-hung, fan flue, gas fired, ErP rated ‘A’ condensing, system boiler, to be sited in the
airing cupboard, complete with gas, water and electrical connections.
FLUE SYSTEM
Extend from boiler turret vertically, terminating externally in the approved manner, using a Worcester Bosch flue kit.
CONDENSATE DISCHARGE
Extend condensate pipework from the boiler to internal, complete with all necessary connections.
CENTRE RAD COMPACT RADIATORS
Locations and sizes to be confirmed with customer preferred locations.
These calculations are based on an outside temperature of -1°C and a boiler flow temperature of 82°C, to conform with the
requirements of BS EN442, 2003. One and a half air changes per hour per room. Under these conditions, these temperatures are
guaranteed.
Plumb in 13 new radiators complete with Danfoss thermostatic & lockshield radiator valves and necessary pipework connections
onto existing heating system, using copper pipe of adequate size, as necessary.
HEATING CIRCUIT IN SMALL-BORE (15 & 22mm)
A two pipe accelerated small-bore system, using copper pipe to BS 2871 and Hep2O plastic pipe to BS 2791, concealed beneath
the 1st floor and dropping down to the ground floor in the most practical manner, so as to hide as much pipe as possible,
concealed within chased walls (no allowances to re-plaster)
CONTROLS
A Honeywell twin channel timer complete with digital, room thermostat sited where necessary.
Electrician to quote for new spur for boiler and immersion supplies.
PUMP
A new pump is factory fitted inside the boiler.
WORCESTER FILTER
A 22mm Worcester filter unit sited adjacent to the boiler, plumbed-in complete with all necessary connections.
HOT WATER
A Worcester Bosch 210 litre unvented indirect cylinder to be sited within airing cupboard.
To run new 22mm cold main from stop tap location to maximise pressure.
To run new D2 pipe to external wall.
MANUAL SYSTEM FLUSHWATER TREATMENT TO BS7593
Introduce Fernox F3 cleaner and flush to drain inline with manufactures instructions.
GENERAL
Run gas supply from meter point, to the boiler, using copper pipe of adequate size, as necessary.
Make good to brickwork and plaster cut out during the course of the installation.
Complete all electrical wiring to heating controls. (Subject to the existing electrical installation being suitable. Some systems may
need upgrading to current safety standards at extra cost).
All rubbish and redundant materials removed from site and allowed for in this quotation.
Commission boiler, as per manufacturers instructions.
Inject system with Fernox Filter Fluid Protector which is specifically formulated to lift corrosion deposits and contaminants within
central heating systems to deliver the debris directly to the Worcester system filter.
System filled, boiler fired, tested and left in working order, for a total cost, including labour and all materials.
Quote 1 - Vaillant ecoTec Plus 30 System boiler
Isolate supplies and drain down water.
Disconnect and remove the existing radiators, boiler and flue.
Supply and install a new Vaillant system boiler and flue to the Cupboard.
Supply and install a system filter.
Supply and install a new 250L unvented hot water cylinder to the Airing Cupboard.
Supply and install new radiators with thermostatic valves to 12 rooms.
Fill the system and flush out, refill with added corrosion inhibitor.
Carry out system water test and report back if there are any issues.
Removal of all waste from the site for recycling/disposal.
Set up and test of the whole system, including a full handover and explanation of the system and controls.
Commission and issue manufacturer's warranty*
Quote 2 - Worcester Greenstar 4000 System boiler 24kW
SUPPLY & FIT:
BOILER
A Worcester Bosch Greenstar 4000 24kw, wall-hung, fan flue, gas fired, ErP rated ‘A’ condensing, system boiler, to be sited in the
airing cupboard, complete with gas, water and electrical connections.
FLUE SYSTEM
Extend from boiler turret vertically, terminating externally in the approved manner, using a Worcester Bosch flue kit.
CONDENSATE DISCHARGE
Extend condensate pipework from the boiler to internal, complete with all necessary connections.
CENTRE RAD COMPACT RADIATORS
Locations and sizes to be confirmed with customer preferred locations.
These calculations are based on an outside temperature of -1°C and a boiler flow temperature of 82°C, to conform with the
requirements of BS EN442, 2003. One and a half air changes per hour per room. Under these conditions, these temperatures are
guaranteed.
Plumb in 13 new radiators complete with Danfoss thermostatic & lockshield radiator valves and necessary pipework connections
onto existing heating system, using copper pipe of adequate size, as necessary.
HEATING CIRCUIT IN SMALL-BORE (15 & 22mm)
A two pipe accelerated small-bore system, using copper pipe to BS 2871 and Hep2O plastic pipe to BS 2791, concealed beneath
the 1st floor and dropping down to the ground floor in the most practical manner, so as to hide as much pipe as possible,
concealed within chased walls (no allowances to re-plaster)
CONTROLS
A Honeywell twin channel timer complete with digital, room thermostat sited where necessary.
Electrician to quote for new spur for boiler and immersion supplies.
PUMP
A new pump is factory fitted inside the boiler.
WORCESTER FILTER
A 22mm Worcester filter unit sited adjacent to the boiler, plumbed-in complete with all necessary connections.
HOT WATER
A Worcester Bosch 210 litre unvented indirect cylinder to be sited within airing cupboard.
To run new 22mm cold main from stop tap location to maximise pressure.
To run new D2 pipe to external wall.
MANUAL SYSTEM FLUSHWATER TREATMENT TO BS7593
Introduce Fernox F3 cleaner and flush to drain inline with manufactures instructions.
GENERAL
Run gas supply from meter point, to the boiler, using copper pipe of adequate size, as necessary.
Make good to brickwork and plaster cut out during the course of the installation.
Complete all electrical wiring to heating controls. (Subject to the existing electrical installation being suitable. Some systems may
need upgrading to current safety standards at extra cost).
All rubbish and redundant materials removed from site and allowed for in this quotation.
Commission boiler, as per manufacturers instructions.
Inject system with Fernox Filter Fluid Protector which is specifically formulated to lift corrosion deposits and contaminants within
central heating systems to deliver the debris directly to the Worcester system filter.
System filled, boiler fired, tested and left in working order, for a total cost, including labour and all materials.