Ok I’ll just say I am a electrician but I’ve been out of the uk for quite a while so not sure on full rules regarding this.
I need to relocate my board too around 5m away from the meter the run would be up the cavity to where the board currently is (Which will be getting patched over) then there is a 200mm chase to the ceiling then into floor space and through maybe 4 joists then board will go ceiling height in final location.
I know the chase needs to be 50mm deep for none armoured none rcd cables, but am I fine just running meter tails through joist, I guess 25mm tails I’d get them in a 32mm hole.
I need to relocate my board too around 5m away from the meter the run would be up the cavity to where the board currently is (Which will be getting patched over) then there is a 200mm chase to the ceiling then into floor space and through maybe 4 joists then board will go ceiling height in final location.
I know the chase needs to be 50mm deep for none armoured none rcd cables, but am I fine just running meter tails through joist, I guess 25mm tails I’d get them in a 32mm hole.