Hi there,
I was wondering if someone could help me. I have spoke with a couple of electricians and UK Power Network and slightly confused.
I have bought a shop that has a maisonette above. The idea is to split the Maisonette above to 2 x 1bed flats. One will be powered on electric (water powered via direct unvented cylinder) and the other will be GCH.
I will also need a landlords supply for the communal hall way, to get a fire alarm system and Automatic Open Vent installed - along with lighting.
Currently, I do not have the intention of doing anything to the shop - this will eventually be converted to a flat, but in couple years time.
The main supply is in the shop, which powers the building. It states the following:
100a BS 1361 Type 2B / Connected to a PME System.
The meter states: Single Phase Watt Hour Meter, Property of London Power Network (2002) - there are four cables coming out of this.
My question is: would this be enough power for what I am currently proposing (2x1beds and landlord connection) and to get UKPN to move this to the communal hall way, get the utility provider to install individual meters and then an electrician to do their part?
Or is this a ridiculous question and UKPN would need to upgrade this to a three phase fuse?
Thank you
I was wondering if someone could help me. I have spoke with a couple of electricians and UK Power Network and slightly confused.
I have bought a shop that has a maisonette above. The idea is to split the Maisonette above to 2 x 1bed flats. One will be powered on electric (water powered via direct unvented cylinder) and the other will be GCH.
I will also need a landlords supply for the communal hall way, to get a fire alarm system and Automatic Open Vent installed - along with lighting.
Currently, I do not have the intention of doing anything to the shop - this will eventually be converted to a flat, but in couple years time.
The main supply is in the shop, which powers the building. It states the following:
100a BS 1361 Type 2B / Connected to a PME System.
The meter states: Single Phase Watt Hour Meter, Property of London Power Network (2002) - there are four cables coming out of this.
My question is: would this be enough power for what I am currently proposing (2x1beds and landlord connection) and to get UKPN to move this to the communal hall way, get the utility provider to install individual meters and then an electrician to do their part?
Or is this a ridiculous question and UKPN would need to upgrade this to a three phase fuse?
Thank you