Sorry folks, I'm almost as slow at keeping this log updated as I am with my actual build!
So back to the story, with the ground finally cleared, with only a day or two spared before the piling contractors were coming, it was cutting it fine. Up to this point I've spent nearly £4k in total which was mostly on the demolition guys (£2.5k), and then having to hire/buy the equipment to finish their job, with nearly £1.5k on the plans, planning and building control costs
I'd been doing a lot of ringing around for piling contractors and found quite a lot of variability in the pricing and the level of helpfulness they'd provide to a DIYer! In the end I found a Wigan-based W&L Piling where the main contact was really helpful and his price was competitive, which included the designs, piles, ring beam, concrete, and the groundworks (inc soil removal) to be ready for the actual foundations. The way it works with piling, is that you're given a base price which covers most things but then you pay an extra cost for every meter down the piles go beyond the quote depth. So in my case the quote included piling to 4m, with £20 (plus Vat) for every meter for every pile beyond that.
The piling guys did a detailed piling design which was sent off to BC beforehand. It was 29 pages in total, but I've clipped a few extracts to include here, but basically required 13 piles in various places:
BC were happy with the plans, but as per normal they would want to inspect before the concrete was poured.
The guys from the piling co turned up on time, and did the groundworks on day 1. Unfortunately I was away for work, so there aren't many pictures from this stage, but as you can see - my house is literally built on nothing but sand and we ended up with a massive pile of it at the end of that day (as modelled by my better half ).
It took the guys a further 3 days for setting the actual piles and ring beams, and was was expected they had to go pretty deep 14m in some places to hit solid ground for the piles - which of course adds a lot to the costs when you have 13 piles at £20 per meter!
I was expecting all sorts of heavy machinery but no such stuff - just these pneumatic rams as seen at the rear of the house in the last picture above.
All the piles were in and building control came out and signed-off on the concrete pour on the 3rd December, so we had a whole 2 days to spare on my nominal deadline of the 6th December which was the 3rd anniversary (and expiry) of the planning permission!
The next day the concrete was poured and we were left with something that actually looked like progress
In the end, the extra depth (beyond 4m) of the piles added near £2k to the estimate, so the total cost of the works was £9.5k including the VAT.
Therefore total spend to this point was £13.5k.
Appreciate that money can be a funny subject for some, but I'm detailing the rough costs as a guide for future readers (baring in mind those prices were 2018 prices in the NW of England), rather than boastful 'look how much we've spent kind of way'. Would be interested if people want to know/care about the costs of if I should just omit from future updates?!
So back to the story, with the ground finally cleared, with only a day or two spared before the piling contractors were coming, it was cutting it fine. Up to this point I've spent nearly £4k in total which was mostly on the demolition guys (£2.5k), and then having to hire/buy the equipment to finish their job, with nearly £1.5k on the plans, planning and building control costs
I'd been doing a lot of ringing around for piling contractors and found quite a lot of variability in the pricing and the level of helpfulness they'd provide to a DIYer! In the end I found a Wigan-based W&L Piling where the main contact was really helpful and his price was competitive, which included the designs, piles, ring beam, concrete, and the groundworks (inc soil removal) to be ready for the actual foundations. The way it works with piling, is that you're given a base price which covers most things but then you pay an extra cost for every meter down the piles go beyond the quote depth. So in my case the quote included piling to 4m, with £20 (plus Vat) for every meter for every pile beyond that.
The piling guys did a detailed piling design which was sent off to BC beforehand. It was 29 pages in total, but I've clipped a few extracts to include here, but basically required 13 piles in various places:
BC were happy with the plans, but as per normal they would want to inspect before the concrete was poured.
The guys from the piling co turned up on time, and did the groundworks on day 1. Unfortunately I was away for work, so there aren't many pictures from this stage, but as you can see - my house is literally built on nothing but sand and we ended up with a massive pile of it at the end of that day (as modelled by my better half ).
It took the guys a further 3 days for setting the actual piles and ring beams, and was was expected they had to go pretty deep 14m in some places to hit solid ground for the piles - which of course adds a lot to the costs when you have 13 piles at £20 per meter!
I was expecting all sorts of heavy machinery but no such stuff - just these pneumatic rams as seen at the rear of the house in the last picture above.
All the piles were in and building control came out and signed-off on the concrete pour on the 3rd December, so we had a whole 2 days to spare on my nominal deadline of the 6th December which was the 3rd anniversary (and expiry) of the planning permission!
The next day the concrete was poured and we were left with something that actually looked like progress
In the end, the extra depth (beyond 4m) of the piles added near £2k to the estimate, so the total cost of the works was £9.5k including the VAT.
Therefore total spend to this point was £13.5k.
Appreciate that money can be a funny subject for some, but I'm detailing the rough costs as a guide for future readers (baring in mind those prices were 2018 prices in the NW of England), rather than boastful 'look how much we've spent kind of way'. Would be interested if people want to know/care about the costs of if I should just omit from future updates?!