I would say to not use approved maintenance free connectors in otherwise suitable enclosure which is not actually specified by the connector manufacturer is bordering on the ridiculous.
If that is the case, that would mean the maintenance free connectors folk may use within a light switch, say for the neutrals, would be completely incorrect.
I think common sense has to overrule some daft manufacturers instructions.
This just protecting their own interests. If Wagos are MF they are MF whatever box they are in surely.But Wagos, and I assume others, are only classed as MF when installed according to the MIs. And the MIs specify the use of their own boxes.
So some random plastic box of Wagos, or similar, doesn't count.
You would certainly think so.This just protecting their own interests. If Wagos are MF they are MF whatever box they are in surely.
This just protecting their own interests. If Wagos are MF they are MF whatever box they are in surely.
AIUI the definition of "MF" referenced by BS7671 is a standard for accessories not terminals. So terminals by themselves can't be "MF". It's the complete assembly that needs to be approved.If Wagos are MF they are MF whatever box they are in surely.
I'm not sure that BS5733, hence BS7671, would necessarily agree with that.If Wagos are MF they are MF whatever box they are in surely.
So, latest update from NICEIC - it's taken some time to get responses!
Thanks again for your help and advice - it's helped a lot!
Tails Length
We're putting in a mechanical switch to protect against overcurrent, in the meter cupboard (as you gents recommended, of course!)
Tails Location / Protection
They proposed to take out the plaster where the cable goes over the pier and fit a metal plate. But this would only really protect the tails when they're just under the plaster.
(OK, sure, they're probably 3 inches below the plaster on the rest of the wall - but they're in prime "picture hanging" space, and I don't like the thought of someone in the future hitting one of them with a drill).
So, we're running the feed using SWA along the outside of the house instead - from the meter to the consumer. (it's lucky this room is a converted garage that allows for that solutions)
Junction Box - Accessibility
NICEIC tried to claim it would be a contractual dispute as the walls were put up after the installation work.
I pointed out to one of their consultants that the electricians work wasn't just to move the consumer - it was running new sockets, cat6, lights, etc - and they came back during the stud going up, and after plastering, to complete their work. It was all the same work - and they were clearly aware that the junction box would be covered up. So it's an oversight by them.
Consultant agreed.
But now NICEIC are trying to claim contractual dispute again (i.e. not their problem).
Meh.
Consumer Not Tested
Consumer wasn't tested when moved. NICEIC are claiming that it's "too long ago" and they cannot "prove or disprove pre-existing circuits were tested".
Well, they're not listed on the test certificate, are they? Electrician also admitted that they 'overlooked' adding the CU move to their worksheet and the CU testing! Awaiting their response....
External Sockets - Not Earthed Correctly
This popped up along the way. External sockets on the property fed by SWA from the CU.
Their expert had concerns that was the Junction Box was plastic - so they can't gland it there. And the pictures show the SWA doesn't go back to the CU to be earthed there either.
Electrician is going to check if sockets are earthed externally - at the sockets - using a brass banjo +/ flying earth lead.
Getting there - slowly.
Still not overly keen on having the cowboys back to 'fix' the work to be frank as they're messing about somewhat.
I'm in two minds about simply getting someone else in to do the work - and do some extra work too (e.g. upgrade the consumer to High Integrity, put some RCBO's in, do a full consumer and circuit test, and a few other bits).
You are not the first person to have said such things!Makes you wonder what the point of having these governing bodies if they don't do anything to the contractor or make the contractor re-do the work. .... It seems like they can't be bothered.
You are not the first person to have said such things!
What you have to understand is that they are not 'governing bodies' but, rather, are commercially-motivated trade organisations.
There is no compulsion on electricians to pay their money to become a member of any of these organisations and, in general, no restriction as to what electrical work can be undertaken by someone who is not a member of one of them. The main difference is that, if a member of such an organisation, they can 'self-certify' ('self-notify') notifiable work, which enables them to significantly reduce the amount a customer has to pay when notifiable work is done.
Kind Regards, John
You'd probably have to ask a lawyer for a definitive answer.But surely they must be performing due diligence otherwise they are authorising sub standard work. What if the customers house burns down due to the notifiable work not being carried out to the required standard?
There is 'accountability' in terms of membership of the organisation. If, following a complaint from a customer, a member is told to remedy defective work but does not do so, or if the member is a 'repeat offender' (in terms of complaints), they can/could be thrown out of the 'club' (if the organisation didn't mind losing their subscription!) but, as far as I am aware, the organisation has no teeth beyond that.Surely there must be a degree of accountability somewhere.
If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.
Select the supplier or trade you require, enter your location to begin your search.
Are you a trade or supplier? You can create your listing free at DIYnot Local